| Estimated timetable for typical single unit construction The single-most time consuming process in building any home is the permit application procedures, which vary with each location and review agencies. Once the permit for construction has been secured the following time table to completion of construction applies.  Week 1Close escrow, permit issued, Arrival journeyman trailer, install prelim. Utility,
 elect. Pole at site, start excavation, site preparation, driveway, rough grading
 start septic system install w/leachfield, all utilities trenched
 perimeter fencing, security, work crew trailer hook up
 Week 2formwork, basement walls, meters, utilities permanent hook-up
 Quadlock system foundation wall installed, complete excavation
 2 conc. pours, cured waterproof exterior walls,
 install perimeter french subgrade drain
 backfill, delivery of first floor framing, finish grading
 Week 3First Floor Glulam beams installed, Trussjoist longspan floor joists installed
 install 1 1/8”plywd. decking, secure perimeter beams
 delivery of SiPs panels, all structural framing members to site
 radiant tubing, manifolds, lightweight conc. First Floor deck poured
 Garage enclosed, finishes installed, secured site
 Week 4ext. waterproofing installation, stairways assembled, rough electrical, rough plumbing & utility systems to house
 start SiPs assembly, shell framing, roof assembly
 Week 5Porch framing, porch SiPs roof assembly
 Pre-finished windows delivered, Sliding doors installation
 close up shell, pour rear slab storage room
 Week 6completion of SiPs panels installation, Bldg enclosed
 installation metal roofing, both levels, frame out second floor loft
 exterior siding, finish electrical, plumbing, HVAC
 
 Week 7
 drywall interior, installation first floor bath fixtures,
          2nd fl. Bath fixtures, finish materials 1st, 2nd Fl. Bath 
          kitchen assembly, fixtures installed
 
 Week 8
 install appliances, kitchen cabinetry, living room cabinetry
 construction assembly of interior stairway/cabinetry, bedroom closet assembly
 completion installation all counters
 Week 9finish wire all appliances, I
 nstallation all fixtures completed
 Week 10install electrical fixtures, lighting, CATV, telephone, mechanical completed,
 painting & sealing
 Week 11floor finish installation, mechanical systems adjustment
 Sign off all subcontractor permits
 screens, screen doors installation
 Week 12Modifications & adjustments, construction delays, changes
 client checklist revisions, modifications exterior landscaping, site finish
 Week 13site cleaning, final inspections, finish grading
 Week 14Certificate of Occupancy issued
 Bldg & Safety sign-off
 Week 15Finish landscaping, access, fencing, debris removal
 Week 16Journeyman labor trailer removal, final client walk-through
 Week 17Client transfer, move-in date
 Total estimated construction per unit from permit issue   4 months     |